Shared-Use
Pathway Repairs

Reconstruction of approximately 6,500 feet of HMA shared-use pathway along N 144th Avenue and Butternut Drive in Park Township, Ottawa County — Project #2260339.

Bidding — June 2, 2026
Client
Park Township
Engineer
Prein & Newhof
Location
N 144th Ave & Butternut Dr
Park Township, MI
Bid Date
June 2, 2026

What We're Bidding

Terracon LLC is bidding the 2026 Park Township Shared-Use Pathway Repairs project for Park Township, Ottawa County. The base bid covers full reconstruction of approximately 6,500 linear feet of HMA shared-use pathway across two corridors: N 144th Avenue from Pine Creek Bridge south to Riley Street, and Butternut Drive from 144th Avenue east to 148th Avenue.

Work includes complete pavement removal, 6-inch 21AA aggregate base compacted to 98% density, and 165 lbs/SYD of MDOT HMA 5EL in two courses (base + top). ADA-compliant concrete ramps will be installed at all road crossings. Modular concrete block retaining walls will replace existing timber walls at two properties on N 144th Avenue.

Two bid alternates expand the project: Add Alternate 1 addresses timber wall removal and regrading at 1933 Ottawa Beach Road near Lake Macatawa. Add Alternate 2 adds approximately 2,700 feet of new 6-foot-wide pathway along Riley Street from 144th Avenue to Christmas Lane.

By the Numbers

6,500 LF
Base Bid Pathway
2,700 LF
Add Alt 2 Pathway
320 SF
Block Retaining Wall
1,000 SF
ADA Concrete Ramps

The two base bid path segments total approximately 4,900 square yards of new HMA surface. The Riley Street alternate adds another 1,800 square yards, bringing the combined project to nearly 9,200 linear feet of improved pathway corridor for Park Township residents and trail users.

Project Scope

Base Bid

N 144th Ave Path

  • ~3,900 LF of 6-ft wide HMA pathway
  • Pine Creek Bridge south to Riley Street
  • Full depth removal & reconstruction
  • 6” 21AA aggregate base at 98%
  • 165 lbs/SYD HMA 5EL, 2 courses
  • ADA ramps at road crossings
  • Modular block wall at 900 & 892 N 144th
  • 6 water service verifications
Base Bid

Butternut Drive Path

  • ~2,600 LF of 8-ft wide HMA pathway
  • 144th Avenue east to 148th Avenue
  • Full depth removal & reconstruction
  • 6” 21AA aggregate base at 98%
  • 165 lbs/SYD HMA 5EL, 2 courses
  • ADA ramps at road crossings
  • Water service verifications along corridor
  • Pavement markings at crossings
Add Alternates

Alternates 1 & 2

  • Alt 1: 1933 Ottawa Beach Rd
  • Timber wall removal & regrading
  • 4 stump removals, full site restoration
  • Consumers Energy guy wire relocation
  • Alt 2: Riley Street Pathway
  • ~2,700 LF new 6-ft wide HMA pathway
  • 144th Avenue to Christmas Lane
  • 6 water services, 4 valve/MH adjustments

Work Locations

The base bid covers two connected pathway segments in Park Township. Add Alternate 1 is located near Lake Macatawa on Ottawa Beach Road (not shown at this zoom). Add Alternate 2 extends the corridor along Riley Street.

Base Bid Path (144th Ave & Butternut Dr)
Add Alt 2 — Riley Street
Retaining Wall Locations
Water Service Verifications

ⓘ Alignment is approximate. Final locations follow project plans and engineer field determination.